April 24, 2020

The president of Olanger Seilbahnen AG - Prugger Matthias confirms that despite the uncertain situation, the construction of the cable car Olang 1+2 will be confirmed.

 

 

April 29, 2020

The haul rope of the Olang 1+2 cable car has been cut and thus gives the symbolic starting signal for the dismantling work at the bottom and middle stations.

 

May 18, 2020

Thanks to the good weather conditions, work on the top station could finally begin.

June 29, 2020

After 61 days of construction, the mountain, middle and valley stations were demolished. In the meantime, construction work is already underway on the new stations.

August 22, 2020

A review of the last 114 days of construction

october 1, 2020

Look forward to the fastest and most innovative cable car at Kronplatz! With the 3D video you can already get first impressions.

october 14, 2020

Despite snowfall, work is progressing well on the middle station.